Timeline

3 months from filing to approval2 months to certification · 1 month of public review

Application and environmental review2 months

  1. Application filedJun 23, 1995The applicant files the land use application with the Department of City Planning.
  2. Environmental reviewMay 20, 1986 · through Sep 23, 1986An environmental assessment, or for big projects a full impact statement, under City Environmental Quality Review.
  3. Certified for public reviewSep 12, 1995The Planning Commission certifies the application complete, and the public review clock starts.

ULURP public review1 month

  1. City Planning Commission voteSep 12, 1995 · ApprovalThe Planning Commission votes within 60 days of the borough president's review.
  2. City CouncilThe Council reviews rezonings and votes within 50 days.
  3. MayorThe mayor may veto within 5 days; the Council can override.
  4. ApprovedOct 17, 1995

The standard Uniform Land Use Review Procedure steps, with the dates the City recorded for this application. Times run from the land use application's filing date. Older applications often have only a few dates on record.

Applicant Team

Applicant80-02 Leasehold CoPrivate applicant
Land-use attorneyRosenman & ColinSee the firm's rezoningsNamed in the City's applicant record

Environmental review CEQR 86-300Q · zoning map amendment M790440FZMQ.