John Walter Edwards Apts

Rezoned areaBasemap: Esri, HERE, Garmin, © OpenStreetMap contributors

91-088K: ULURP-RELATED TO CONSTRUCTION 7-STORY, 100 DWELLING UNIT BUILDING UNDER SECTION 202

Outcome
Approved
Zoning map ULURP
C910360ZMK
Rezoned area
2.9 acres
Law firm
—

Timeline

9 months from filing to approval4 months to certification · 4 months of public review

Application and environmental review4 months

  1. Application filedMar 18, 1991The applicant files the land use application with the Department of City Planning.
  2. Environmental reviewNov 15, 1990An environmental assessment, or for big projects a full impact statement, under City Environmental Quality Review.
  3. Certified for public reviewJul 29, 1991 · CertifiedThe Planning Commission certifies the application complete, and the public review clock starts.

ULURP public review4 months

  1. Community boardSep 30, 1991 · Approved with ConditionsUp to 60 days for the community board's advisory recommendation.
  2. Borough presidentOct 25, 1991 · Conditional FavorableUp to 30 days for the borough president's recommendation.
  3. City Planning Commission hearingNov 6, 1991 · Hearing ClosedThe Planning Commission's public hearing.
  4. City Planning Commission voteDec 4, 1991 · ApprovalThe Planning Commission votes within 60 days of the borough president's review.
  5. City CouncilDec 19, 1991 · AdoptedThe Council reviews rezonings and votes within 50 days.
  6. MayorDec 24, 1991 · No VetoThe mayor may veto within 5 days; the Council can override.
  7. ApprovedDec 24, 1991

The standard Uniform Land Use Review Procedure steps, with the dates the City recorded for this application. Times run from the land use application's filing date. Older applications often have only a few dates on record.

Applicant Team

ApplicantHpdOther Public Agency

Environmental review CEQR 91-088K · zoning map amendment C910360ZMK.

Source: the NYC Department of City Planning's Zoning Application Portal, project P1991K0306, as of 2026-11-19. The law firm and consultant are as the City's documents name them. The map outline is the City's map of zoning changes.