Kew Gardens Office Tower
86-300Q: 17 STORY PLUS MECHANICAL PENTHOUSE COMMERCIAL AND COMMUNITY FACILITY
- Outcome
- Approved
- Zoning map ULURP
- M790440CZMQ
- Rezoned area
- —
- Law firm
- McGee & Morsellino
Timeline
1 year, 6 months from filing to approval1 year, 3 months to certification · 2 months of public review
Application and environmental review1 year, 3 months
- Application filedDec 17, 1987The applicant files the land use application with the Department of City Planning.
- Environmental reviewMay 20, 1986 · through Sep 23, 1986An environmental assessment, or for big projects a full impact statement, under City Environmental Quality Review.
- Certified for public reviewApr 3, 1989The Planning Commission certifies the application complete, and the public review clock starts.
ULURP public review2 months
- Community boardNo date on recordUp to 60 days for the community board's advisory recommendation.
- Borough presidentNo date on recordUp to 30 days for the borough president's recommendation.
- City Planning Commission hearingNo date on recordThe Planning Commission's public hearing.
- City Planning Commission voteJun 22, 1989 · ApprovalThe Planning Commission votes within 60 days of the borough president's review.
- City CouncilThe Council reviews rezonings and votes within 50 days.
- MayorThe mayor may veto within 5 days; the Council can override.
- ApprovedJun 22, 1989
The standard Uniform Land Use Review Procedure steps, with the dates the City recorded for this application. Times run from the land use application's filing date. Older applications often have only a few dates on record.
Applicant Team
Environmental review CEQR 86-300Q · zoning map amendment M790440CZMQ.
Source: the NYC Department of City Planning's Zoning Application Portal, project P1988Q0423, as of 2026-11-19. The law firm and consultant are as the City's documents name them. The map outline is the City's map of zoning changes.
See Top NYC Rezoning Attorneys and which NYC condos were built on rezoned land.