THE CONDO BOOK PROJECT

Madison Ave, E60th St, E61st St

Rezoned areaBasemap: Esri, HERE, Garmin, © OpenStreetMap contributors

ESTABLISH SPECIAL MIDTOWN DISTRICT(MID) & CHANGE C5-1 TO*C5-3

Outcome
Approved
Zoning map ULURP
C820798ZMM
Rezoned area
2.8 acres
Law firm
—

Timeline

4 months from filing to approval12 days to certification · 4 months of public review

Application and environmental review12 days

  1. Application filedMar 4, 1982The applicant files the land use application with the Department of City Planning.
  2. Certified for public reviewMar 16, 1982 · CertifiedThe Planning Commission certifies the application complete, and the public review clock starts.

ULURP public review4 months

  1. Community boardMay 21, 1982 · ApprovedUp to 60 days for the community board's advisory recommendation.
  2. City Planning Commission hearingJun 2, 1982 · Hearing ClosedThe Planning Commission's public hearing.
  3. City Planning Commission voteJun 16, 1982 · ApprovalThe Planning Commission votes within 60 days of the borough president's review.
  4. City CouncilThe Council reviews rezonings and votes within 50 days.
  5. MayorThe mayor may veto within 5 days; the Council can override.
  6. ApprovedJul 22, 1982

The standard Uniform Land Use Review Procedure steps, with the dates the City recorded for this application. Times run from the land use application's filing date. Older applications often have only a few dates on record.

Applicant Team

ApplicantDcpDepartment of City Planning

Source: the NYC Department of City Planning's Zoning Application Portal, project P1982M0705, as of 2026-11-19. The law firm and consultant are as the City's documents name them. The map outline is the City's map of zoning changes.