Marriott Hotel
CHANGE R3-2 TO C4-2 TO PERM CONSTRUCTON OF MARRIOTT HOTEL*(ALTERNAT PROP)
- Outcome
- Approved
- Zoning map ULURP
- C790347ZMQ
- Rezoned area
- 12.1 acres
- Law firm
- —
Timeline
2 years, 6 months from filing to approval10 days to certification · 2 years, 6 months of public review
Application and environmental review10 days
- Application filedJun 1, 1979The applicant files the land use application with the Department of City Planning.
- Environmental reviewNo date on recordAn environmental assessment, or for big projects a full impact statement, under City Environmental Quality Review.
- Certified for public reviewJun 11, 1979 · CertifiedThe Planning Commission certifies the application complete, and the public review clock starts.
ULURP public review2 years, 6 months
- Community boardJul 5, 1979 · ApprovedUp to 60 days for the community board's advisory recommendation.
- Borough presidentNo date on recordUp to 30 days for the borough president's recommendation.
- City Planning Commission hearingJul 11, 1979 · Hearing ClosedThe Planning Commission's public hearing.
- City Planning Commission voteJul 11, 1979 · ApprovalThe Planning Commission votes within 60 days of the borough president's review.
- City CouncilThe Council reviews rezonings and votes within 50 days.
- MayorThe mayor may veto within 5 days; the Council can override.
- ApprovedDec 22, 1981
The standard Uniform Land Use Review Procedure steps, with the dates the City recorded for this application. Times run from the land use application's filing date. Older applications often have only a few dates on record.
Applicant Team
ApplicantW.S. Johnson Properties, IncPrivate applicant
Source: the NYC Department of City Planning's Zoning Application Portal, project P1979Q0634, as of 2026-11-19. The law firm and consultant are as the City's documents name them. The map outline is the City's map of zoning changes.