THE CONDO BOOK PROJECT

Melrose Commons Rfp Site B-1

Rezoned areaBasemap: Esri, HERE, Garmin, © OpenStreetMap contributors

ELIMINATE R8/C1-4 OVERLAY TO ENABLE THE BLDG DESIGN TO*MATCH THE NEIGHBORHOOD CONTEXT

Outcome
Approved
Zoning map ULURP
C080002ZMX
Rezoned area
0.6 acres
Law firm
—

Timeline

4 months from filing to approval7 days to certification · 3 months of public review

Application and environmental review7 days

  1. Application filedJul 2, 2007The applicant files the land use application with the Department of City Planning.
  2. Certified for public reviewJul 9, 2007 · CertifiedThe Planning Commission certifies the application complete, and the public review clock starts.

ULURP public review3 months

  1. Community boardAug 5, 2007 · ApprovedUp to 60 days for the community board's advisory recommendation.
  2. Borough presidentAug 28, 2007 · FavorableUp to 30 days for the borough president's recommendation.
  3. City Planning Commission hearingSep 19, 2007 · Hearing ClosedThe Planning Commission's public hearing.
  4. City Planning Commission voteOct 3, 2007 · ApprovalThe Planning Commission votes within 60 days of the borough president's review.
  5. City CouncilOct 29, 2007 · AdoptedThe Council reviews rezonings and votes within 50 days.
  6. MayorNov 3, 2007 · No VetoThe mayor may veto within 5 days; the Council can override.
  7. ApprovedNov 3, 2007

The standard Uniform Land Use Review Procedure steps, with the dates the City recorded for this application. Times run from the land use application's filing date. Older applications often have only a few dates on record.

Applicant Team

ApplicantHpdOther Public Agency

Source: the NYC Department of City Planning's Zoning Application Portal, project P2008X0001, as of 2026-11-19. The law firm and consultant are as the City's documents name them. The map outline is the City's map of zoning changes.