THE CONDO BOOK PROJECT

Morris Park Ave & Williamsbridge Rd

Rezoned areaBasemap: Esri, HERE, Garmin, © OpenStreetMap contributors

CHANGE R3-2 & R4 TO C1-2

Outcome
Approved
Zoning map ULURP
C770073ZMX
Rezoned area
2.6 acres
Law firm
—

Timeline

11 months from filing to approval5 months to certification · 6 months of public review

Application and environmental review5 months

  1. Application filedFeb 18, 1977The applicant files the land use application with the Department of City Planning.
  2. Certified for public reviewAug 1, 1977 · CertifiedThe Planning Commission certifies the application complete, and the public review clock starts.

ULURP public review6 months

  1. Community boardOct 7, 1977Up to 60 days for the community board's advisory recommendation.
  2. City Planning Commission hearingNov 9, 1977 · Hearing ClosedThe Planning Commission's public hearing.
  3. City Planning Commission voteDec 7, 1977 · ApprovalThe Planning Commission votes within 60 days of the borough president's review.
  4. City CouncilThe Council reviews rezonings and votes within 50 days.
  5. MayorThe mayor may veto within 5 days; the Council can override.
  6. ApprovedFeb 2, 1978

The standard Uniform Land Use Review Procedure steps, with the dates the City recorded for this application. Times run from the land use application's filing date. Older applications often have only a few dates on record.

Applicant Team

ApplicantEuropean American Bank & Trust CoPrivate applicant

Source: the NYC Department of City Planning's Zoning Application Portal, project P1977X0237, as of 2026-11-19. The law firm and consultant are as the City's documents name them. The map outline is the City's map of zoning changes.

See Top NYC Rezoning Attorneys and which NYC condos were built on rezoned land.