THE CONDO BOOK PROJECT
Rezoned areaBasemap: Esri, HERE, Garmin, © OpenStreetMap contributors

This is a private application by MSK requesting a zoning map amendment from R8 to R9, text amendment to ZR 79-43, authorizations per ZR 79-21, a ZR 79-43 special permit, modifications to the Large Scale Community Facility Development and Restrictive Declaration, a ZR 26-15 certification and a revocable consent to facilitate a new 31-story hospital building with a pedestrian bridge over 67th Street, within the existing MSK campus’ LSCFD, at 1233 York Avenue, in the Manhattan Community District 8.

Outcome
Approved
Zoning map ULURP
C240237ZMM
Rezoned area
1.2 acres
Law firm
Friedman & Gotbaum LLP

Timeline

1 year, 6 months from filing to approval3 months to certification · 1 year, 2 months of public review

Application and environmental review3 months

  1. Application filedJan 13, 2024The applicant files the land use application with the Department of City Planning.
  2. Environmental reviewMar 27, 2023 · through Jul 26, 2024An environmental assessment, or for big projects a full impact statement, under City Environmental Quality Review.
  3. Certified for public reviewMay 8, 2024 · CertifiedThe Planning Commission certifies the application complete, and the public review clock starts.

ULURP public review1 year, 2 months

  1. Community boardMay 15, 2024 · Approved with ConditionsUp to 60 days for the community board's advisory recommendation.
  2. Borough presidentJun 14, 2024 · Multiple Borough President RecommendationsUp to 30 days for the borough president's recommendation.
  3. City Planning Commission hearingJun 26, 2024 · Hearing ClosedThe Planning Commission's public hearing.
  4. City Planning Commission voteAug 7, 2024 · ApprovalThe Planning Commission votes within 60 days of the borough president's review.
  5. City CouncilSep 26, 2024 · AdoptedThe Council reviews rezonings and votes within 50 days.
  6. MayorOct 1, 2024 · No VetoThe mayor may veto within 5 days; the Council can override.
  7. ApprovedJul 24, 2025

The standard Uniform Land Use Review Procedure steps, with the dates the City recorded for this application. Times run from the land use application's filing date. Older applications often have only a few dates on record.

Applicant Team

ApplicantMemorial Sloan Kettering Cancer Center (MSKCC)Private applicant
Land-use attorneyShelly FriedmanFriedman & Gotbaum LLPNamed as the applicant contact on the City's notice of certification (C 240235 ZSM.NOC.pdf)

Environmental review CEQR 23DCP118M · zoning map amendment C240237ZMM.

City Documents

Application and notices46 documents
Environmental review68 documents
Hearings and presentations3 documents
Approvals and reports30 documents
Other2 documents

Source: the NYC Department of City Planning's Zoning Application Portal, project 2022M0359, as of 2026-11-19. The law firm and consultant are as the City's documents name them. The map outline is the City's map of zoning changes.