PROPOSED C1-3 ZONING FROM EXISTING R7-1 TO PERMIT*DEVELOPMENT OF PUBLIC PARKING LOT FOR 95 CARS

Outcome
Approved
Zoning map ULURP
C830592ZMK
Rezoned area
0.7 acres
Law firm
—

Timeline

6 months from filing to approval3 months to certification · 3 months of public review

Application and environmental review3 months

  1. Application filedFeb 9, 1983The applicant files the land use application with the Department of City Planning.
  2. Certified for public reviewMay 17, 1983The Planning Commission certifies the application complete, and the public review clock starts.

ULURP public review3 months

  1. Community boardMay 17, 1983 · ApprovedUp to 60 days for the community board's advisory recommendation.
  2. City Planning Commission hearingJun 22, 1983 · Hearing ClosedThe Planning Commission's public hearing.
  3. City Planning Commission voteJul 13, 1983 · ApprovalThe Planning Commission votes within 60 days of the borough president's review.
  4. City CouncilThe Council reviews rezonings and votes within 50 days.
  5. MayorThe mayor may veto within 5 days; the Council can override.
  6. ApprovedAug 18, 1983

The standard Uniform Land Use Review Procedure steps, with the dates the City recorded for this application. Times run from the land use application's filing date. Older applications often have only a few dates on record.

Applicant Team

ApplicantRaczko, WilliamPrivate applicant

Source: the NYC Department of City Planning's Zoning Application Portal, project P1983K0554, as of 2026-11-19. The law firm and consultant are as the City's documents name them. The map outline is the City's map of zoning changes.