New York City Borough - Based Jail System

Rezoned areaBasemap: Esri, HERE, Garmin, © OpenStreetMap contributors

New York City Mayor's Office of Criminal Justice and Department of Corrections are proposing to implement a borough-based jail system as part of the City’s continued commitment to create a modern, humane and safe justice system. The proposed project would develop four new detention facilities to house individuals who are in the City’s correctional custody with one located in each of the Bronx, Brooklyn, Manhattan, and Queens. MIH is proposed to be mapped on western portion of the Bronx site.

Outcome
Approved
Zoning map ULURP
C190336ZMX
Rezoned area
1.2 acres
Law firm
—

Timeline

1 year from filing to approval5 months to certification · 7 months of public review

Application and environmental review5 months

  1. Application filedOct 24, 2018The applicant files the land use application with the Department of City Planning.
  2. Environmental reviewOct 3, 2018 · through Aug 30, 2019An environmental assessment, or for big projects a full impact statement, under City Environmental Quality Review.
  3. Certified for public reviewMar 25, 2019 · CertifiedThe Planning Commission certifies the application complete, and the public review clock starts.

ULURP public review7 months

  1. Community boardJun 3, 2019Up to 60 days for the community board's advisory recommendation.
  2. Borough presidentJul 3, 2019 · Multiple Borough President RecommendationsUp to 30 days for the borough president's recommendation.
  3. City Planning Commission hearingJul 10, 2019 · Hearing ClosedThe Planning Commission's public hearing.
  4. City Planning Commission voteSep 3, 2019 · Approval with ModificationThe Planning Commission votes within 60 days of the borough president's review.
  5. City CouncilOct 16, 2019 · CC refers modification application back to CPCThe Council reviews rezonings and votes within 50 days.
  6. MayorOct 22, 2019 · No VetoThe mayor may veto within 5 days; the Council can override.
  7. ApprovedNov 20, 2019

The standard Uniform Land Use Review Procedure steps, with the dates the City recorded for this application. Times run from the land use application's filing date. Older applications often have only a few dates on record.

Applicant Team

ApplicantDocOther Public Agency
Applicant's contactDOC - Department of CorrectionsPrimary contact on the City's record

Environmental review CEQR 18DOC001Y · zoning map amendment C190336ZMX.

City Documents

Building and site26 documents

Source: the NYC Department of City Planning's Zoning Application Portal, project 2019Y0061, as of 2026-11-19. The law firm and consultant are as the City's documents name them. The map outline is the City's map of zoning changes.