Nyu Core, Mercer St., Bleecker St.
11DCP121M: NYU IS SEEKING A NUMBER OF DISCRETIONARY ACTONS IN CONNECTIO N W/ THE PROPOSED EXPANSION OF NYU FACILITIES AS ITS ACADEMI C CORE NEAR WASHINGTON SQUARE
- Outcome
- Approved
- Zoning map ULURP
- C120122ZMM
- Rezoned area
- 17.1 acres
- Law firm
- —
Timeline
7 months from filing to approval29 days to certification · 6 months of public review
Application and environmental review29 days
- Application filedDec 5, 2011The applicant files the land use application with the Department of City Planning.
- Environmental reviewApr 12, 2011 · through Apr 25, 2012An environmental assessment, or for big projects a full impact statement, under City Environmental Quality Review.
- Certified for public reviewJan 3, 2012 · CertifiedThe Planning Commission certifies the application complete, and the public review clock starts.
ULURP public review6 months
- Community boardMar 12, 2012 · ApprovedUp to 60 days for the community board's advisory recommendation.
- Borough presidentApr 11, 2012 · Conditional FavorableUp to 30 days for the borough president's recommendation.
- City Planning Commission hearingApr 25, 2012 · Hearing ClosedThe Planning Commission's public hearing.
- City Planning Commission voteJun 6, 2012 · ApprovalThe Planning Commission votes within 60 days of the borough president's review.
- City CouncilJul 31, 2012 · AdoptedThe Council reviews rezonings and votes within 50 days.
- MayorJul 31, 2012 · No VetoThe mayor may veto within 5 days; the Council can override.
- ApprovedJul 31, 2012
The standard Uniform Land Use Review Procedure steps, with the dates the City recorded for this application. Times run from the land use application's filing date. Older applications often have only a few dates on record.
Applicant Team
Environmental review CEQR 11DCP121M · zoning map amendment C120122ZMM.
City Documents
Environmental review88 documents
- DEIS 00 Executive Summary
- DEIS 01 Project Description
- DEIS 02 Land Use, Zoning, and Public Policy
- DEIS 03 Socioeconomic Conditions
- DEIS 04 Community Facilities and Services
- DEIS 05 Open Space
- DEIS 06 Shadows
- DEIS 07 Historic and Cultural Resources
- DEIS 08 Urban Design and Visual Resources
- DEIS 09 Natural Resources
- DEIS 10 Hazardous Materials
- DEIS 11 Water and Sewer Infrastructure
- DEIS 12 Solid Waste and Sanitation Services
- DEIS 13 Energy
- DEIS 14 Transportation
- DEIS 15 Air Quality
- DEIS 16 Greenhouse Gas Emissions
- DEIS 17 Noise
- DEIS 18 Public Health
- DEIS 19 Neighborhood Character
- DEIS 20 Construction
- DEIS 21 Mitigation
- DEIS 22 Alternatives
- DEIS 23 Unavoidable Adverse Impacts
- DEIS 24 Growth Inducing Aspects of the Proposed Project
- DEIS 25 Irreversible and Irretrievable Commitments of Resources
- DEIS Appendix A Open Space
- DEIS Appendix B Historic and Cultural Resources
- DEIS Appendix C Natural Resources
- DEIS Appendix D Noise
- DEIS Appendix E Construction
- DEIS Appendix F Agency Correspondence
- DEIS Cover Page and Table of Contents
- DEIS Notice Of Completion Dec 30, 2011
- Draft Scope Of Work Apr 15, 2011
- EAS Apr 15, 2011
- FEIS 00 Executive Summary
- FEIS 01 Project Description
- FEIS 02 Land Use, Zoning and Public Policy
- FEIS 03 Socioeconomic Conditions
- FEIS 04 Community Facilities and Services
- FEIS 05 Open Space
- FEIS 06 Shadows
- FEIS 07 Historical and Cultural Resources
- FEIS 08 Urban Design & Visual Resources
- FEIS 09 Natural Resources
- FEIS 10 Hazardous Materials
- FEIS 11 Water and Sewer Infrastructure
- FEIS 12 Solid Waste and Sanitation Services
- FEIS 13 Energy
- FEIS 14 Transportation
- FEIS 15 Air Quality
- FEIS 16 Greenhouse Gas Emissions
- FEIS 17 Noise
- FEIS 18 Public Health
- FEIS 19 Neighborhood Character
- FEIS 20 Construction
- FEIS 21 Mitigation
- FEIS 22 Alternatives
- FEIS 23 Unavoidable Adverse Impacts
- FEIS 24 Growth-Inducing Aspects of the Proposed Projects
- FEIS 25 Irreversible and Irretrievable Commitments of Resources
- FEIS 26 Potential Modifications under Consideration by the City Planning Commission
- FEIS 27 Responses to Comments on the DEIS
- FEIS Appendix A Open Space
- FEIS Appendix B Historic and Cultural Resources
- FEIS Appendix C Natural Resources
- FEIS Appendix D Noise
- FEIS Appendix E Construction Impacts
- FEIS Appendix F Agency Correspondence
- FEIS Appendix G Shadows
- FEIS Appendix H Potential Modifications under Consideration by the NYC City Planning Commission
- FEIS Appendix I Responses to Comments Received on the NYU Core Draft Scope of Work
- FEIS Appendix J Community Boards
- FEIS Appendix J Cover Page on Written Comments Received on the DSOW and DEIS
- FEIS Appendix J Elected Officials
- FEIS Appendix J GVSHP Gibson Dunn Report
- FEIS Appendix J Interested Public
- FEIS Appendix J NYU Core Draft Scope of Work (DSOW) Comments
- FEIS Appendix J Organizations
- FEIS Cover and Table of Contents
- FEIS Foreword
- FEIS Notice Of Completion May 25, 2012
- Final Scope Of Work Dec 30, 2011
- Lead Agency Letter Apr 22, 2011
- Notice Of Scoping Meeting Apr 22, 2011
- Positive Declaration Apr 22, 2011
- Tech Memo Jun 4, 2012
Hearings and presentations1 document
- Notice Of Public Hearing Apr 10, 2012
Source: the NYC Department of City Planning's Zoning Application Portal, project P2012M0059, as of 2026-11-19. The law firm and consultant are as the City's documents name them. The map outline is the City's map of zoning changes.