THE CONDO BOOK PROJECT
Rezoned areaBasemap: Esri, HERE, Garmin, © OpenStreetMap contributors

CHANGE R3-1 TO C1-2 (RICHM RD BET LONGVIEW RD & CONCORD*PL), C8-1 TO C1-2 (RICHM RD BET DEKALB & PIERCE STS), C8-1*TO R3-2 (RHINE AVE BET DEKALB & PIERCE STS)

Outcome
Approved
Zoning map ULURP
C770099ZMR
Rezoned area
3.6 acres
Law firm
—

Timeline

1 year, 7 months from filing to approval1 year, 2 months to certification · 5 months of public review

Application and environmental review1 year, 2 months

  1. Application filedMar 7, 1977The applicant files the land use application with the Department of City Planning.
  2. Certified for public reviewMay 22, 1978 · CertifiedThe Planning Commission certifies the application complete, and the public review clock starts.

ULURP public review5 months

  1. Community boardJul 31, 1978 · DisapprovedUp to 60 days for the community board's advisory recommendation.
  2. City Planning Commission hearingSep 25, 1978 · Hearing ClosedThe Planning Commission's public hearing.
  3. City Planning Commission voteSep 25, 1978 · Approval with ModificationThe Planning Commission votes within 60 days of the borough president's review.
  4. City CouncilThe Council reviews rezonings and votes within 50 days.
  5. MayorThe mayor may veto within 5 days; the Council can override.
  6. ApprovedNov 2, 1978

The standard Uniform Land Use Review Procedure steps, with the dates the City recorded for this application. Times run from the land use application's filing date. Older applications often have only a few dates on record.

Applicant Team

ApplicantBachmann, JPrivate applicant

Source: the NYC Department of City Planning's Zoning Application Portal, project P1977R0253, as of 2026-11-19. The law firm and consultant are as the City's documents name them. The map outline is the City's map of zoning changes.

See Top NYC Rezoning Attorneys and which NYC condos were built on rezoned land.