Outcome
Approved
Zoning map ULURP
C770273ZMR
Rezoned area
51.8 acres
Law firm
—

Timeline

5 months from filing to approval2 months to certification · 3 months of public review

Application and environmental review2 months

  1. Application filedJun 7, 1977The applicant files the land use application with the Department of City Planning.
  2. Certified for public reviewAug 10, 1977The Planning Commission certifies the application complete, and the public review clock starts.

ULURP public review3 months

  1. Community boardOct 5, 1977 · ApprovedUp to 60 days for the community board's advisory recommendation.
  2. City Planning Commission hearingOct 26, 1977 · Hearing ClosedThe Planning Commission's public hearing.
  3. City Planning Commission voteNov 9, 1977 · ApprovalThe Planning Commission votes within 60 days of the borough president's review.
  4. City CouncilThe Council reviews rezonings and votes within 50 days.
  5. MayorThe mayor may veto within 5 days; the Council can override.
  6. ApprovedDec 1, 1977

The standard Uniform Land Use Review Procedure steps, with the dates the City recorded for this application. Times run from the land use application's filing date. Older applications often have only a few dates on record.

Applicant Team

ApplicantDcpDepartment of City Planning

Source: the NYC Department of City Planning's Zoning Application Portal, project P1977R0378, as of 2026-11-19. The law firm and consultant are as the City's documents name them. The map outline is the City's map of zoning changes.

See Top NYC Rezoning Attorneys and which NYC condos were built on rezoned land.