THE CONDO BOOK PROJECT
Rezoned areaBasemap: Esri, HERE, Garmin, © OpenStreetMap contributors

CHANGE R4 TO R1-2 TO BRING AREA INTO CONFORMITY WITH*ADJACENT R1-2 ZONES

Outcome
Approved
Zoning map ULURP
C800931ZMX
Rezoned area
2.8 acres
Law firm
—

Timeline

3 months from filing to approval6 days to certification · 3 months of public review

Application and environmental review6 days

  1. Application filedOct 8, 1980The applicant files the land use application with the Department of City Planning.
  2. Certified for public reviewOct 14, 1980 · CertifiedThe Planning Commission certifies the application complete, and the public review clock starts.

ULURP public review3 months

  1. Community boardNov 12, 1980 · ApprovedUp to 60 days for the community board's advisory recommendation.
  2. City Planning Commission hearingDec 10, 1980 · Hearing ClosedThe Planning Commission's public hearing.
  3. City Planning Commission voteDec 10, 1980 · ApprovalThe Planning Commission votes within 60 days of the borough president's review.
  4. City CouncilThe Council reviews rezonings and votes within 50 days.
  5. MayorThe mayor may veto within 5 days; the Council can override.
  6. ApprovedJan 15, 1981

The standard Uniform Land Use Review Procedure steps, with the dates the City recorded for this application. Times run from the land use application's filing date. Older applications often have only a few dates on record.

Applicant Team

ApplicantDcp-Bronx OfficeDepartment of City Planning

Source: the NYC Department of City Planning's Zoning Application Portal, project P1981X0291, as of 2026-11-19. The law firm and consultant are as the City's documents name them. The map outline is the City's map of zoning changes.