Outcome
Approved
Zoning map ULURP
C030194AZMK
Rezoned area
—
Law firm
—

Timeline

3 months from filing to approval1 month to certification · 2 months of public review

Application and environmental review1 month

  1. Application filedJan 26, 2003The applicant files the land use application with the Department of City Planning.
  2. Environmental reviewNov 15, 2002An environmental assessment, or for big projects a full impact statement, under City Environmental Quality Review.
  3. Certified for public reviewFeb 26, 2003The Planning Commission certifies the application complete, and the public review clock starts.

ULURP public review2 months

  1. City Planning Commission hearingMar 5, 2003 · Hearing ClosedThe Planning Commission's public hearing.
  2. City Planning Commission voteApr 2, 2003 · ApprovalThe Planning Commission votes within 60 days of the borough president's review.
  3. City CouncilApr 30, 2003 · AdoptedThe Council reviews rezonings and votes within 50 days.
  4. MayorMay 5, 2003 · No VetoThe mayor may veto within 5 days; the Council can override.
  5. ApprovedMay 5, 2003

The standard Uniform Land Use Review Procedure steps, with the dates the City recorded for this application. Times run from the land use application's filing date. Older applications often have only a few dates on record.

Applicant Team

ApplicantDcpDepartment of City Planning

Environmental review CEQR 03DCP030K · zoning map amendment C030194AZMK.

Source: the NYC Department of City Planning's Zoning Application Portal, project P2003K0253, as of 2026-11-19. The law firm and consultant are as the City's documents name them. The map outline is the City's map of zoning changes.