THE CONDO BOOK PROJECT

Penn Center Subdistrict

Rezoned areaBasemap: Esri, HERE, Garmin, © OpenStreetMap contributors

01DCP063M: ZONING MAP AND TEXT CHANGE TO CREATE A NEW PENN CENTER SUBDI STRICT (AN EXTENSION OF THE SPECIAL MIDTOWN DISTRICT), AND T O CREATE SPECIAL REGULATIONS FOR THE SUBDISTRICT

Outcome
Approved
Zoning map ULURP
C010652ZMM
Rezoned area
9.7 acres
Law firm
Rosenman & Colin

Timeline

5 months from filing to approval3 days to certification · 5 months of public review

Application and environmental review3 days

  1. Application filedMay 18, 2001The applicant files the land use application with the Department of City Planning.
  2. Environmental reviewApr 16, 2001An environmental assessment, or for big projects a full impact statement, under City Environmental Quality Review.
  3. Certified for public reviewMay 21, 2001 · CertifiedThe Planning Commission certifies the application complete, and the public review clock starts.

ULURP public review5 months

  1. Community boardJun 20, 2001 · DisapprovedUp to 60 days for the community board's advisory recommendation.
  2. Borough presidentJul 20, 2001 · Conditional FavorableUp to 30 days for the borough president's recommendation.
  3. City Planning Commission hearingJul 25, 2001 · Hearing ClosedThe Planning Commission's public hearing.
  4. City Planning Commission voteOct 10, 2001 · ApprovalThe Planning Commission votes within 60 days of the borough president's review.
  5. City CouncilOct 31, 2001 · AdoptedThe Council reviews rezonings and votes within 50 days.
  6. MayorNov 5, 2001 · No VetoThe mayor may veto within 5 days; the Council can override.
  7. ApprovedNov 5, 2001

The standard Uniform Land Use Review Procedure steps, with the dates the City recorded for this application. Times run from the land use application's filing date. Older applications often have only a few dates on record.

Applicant Team

ApplicantVornado DevelopmentPrivate applicant
Land-use attorneyRosenman & ColinSee the firm's rezoningsNamed in the City's applicant record

Environmental review CEQR 01DCP063M · zoning map amendment C010652ZMM.

Source: the NYC Department of City Planning's Zoning Application Portal, project P2001M0372, as of 2026-11-19. The law firm and consultant are as the City's documents name them. The map outline is the City's map of zoning changes.