THE CONDO BOOK PROJECT
Rezoned areaBasemap: Esri, HERE, Garmin, © OpenStreetMap contributors

ZO MAP CHANGE TO EXT C2-2 DIST OVER R2 FOR REMAINDER OF*BLOCK

Outcome
Approved
Zoning map ULURP
C800849ZMQ
Rezoned area
1.8 acres
Law firm
—

Timeline

1 year, 3 months from filing to approval5 months to certification · 9 months of public review

Application and environmental review5 months

  1. Application filedSep 16, 1980The applicant files the land use application with the Department of City Planning.
  2. Certified for public reviewMar 9, 1981 · CertifiedThe Planning Commission certifies the application complete, and the public review clock starts.

ULURP public review9 months

  1. Community boardMay 14, 1981 · Non-ComplyingUp to 60 days for the community board's advisory recommendation.
  2. City Planning Commission hearingJul 13, 1981 · Hearing ClosedThe Planning Commission's public hearing.
  3. City Planning Commission voteJul 13, 1981 · ApprovalThe Planning Commission votes within 60 days of the borough president's review.
  4. City CouncilThe Council reviews rezonings and votes within 50 days.
  5. MayorThe mayor may veto within 5 days; the Council can override.
  6. ApprovedDec 17, 1981

The standard Uniform Land Use Review Procedure steps, with the dates the City recorded for this application. Times run from the land use application's filing date. Older applications often have only a few dates on record.

Applicant Team

ApplicantPlayland Center IncPrivate applicant

Source: the NYC Department of City Planning's Zoning Application Portal, project P1981Q0222, as of 2026-11-19. The law firm and consultant are as the City's documents name them. The map outline is the City's map of zoning changes.