Richmond Ave Bnd By Park Dr East
SITE SELECT & ACQ IN ORDER TO CONST A SANITATION DEPT*GARAGE& SALT STORAGE SHED FOR CD-2
- Outcome
- Approved
- Zoning map ULURP
- C830300ZMR
- Rezoned area
- 7.4 acres
- Law firm
- —
Timeline
1 year, 8 months from filing to approval1 year, 4 months to certification · 4 months of public review
Application and environmental review1 year, 4 months
- Application filedOct 20, 1982The applicant files the land use application with the Department of City Planning.
- Environmental reviewOct 28, 1982An environmental assessment, or for big projects a full impact statement, under City Environmental Quality Review.
- Certified for public reviewMar 12, 1984 · CertifiedThe Planning Commission certifies the application complete, and the public review clock starts.
ULURP public review4 months
- Community boardMay 21, 1984 · Non-ComplyingUp to 60 days for the community board's advisory recommendation.
- Borough presidentNo date on recordUp to 30 days for the borough president's recommendation.
- City Planning Commission hearingMay 30, 1984 · Hearing ClosedThe Planning Commission's public hearing.
- City Planning Commission voteJun 20, 1984 · ApprovalThe Planning Commission votes within 60 days of the borough president's review.
- City CouncilThe Council reviews rezonings and votes within 50 days.
- MayorThe mayor may veto within 5 days; the Council can override.
- ApprovedJul 12, 1984
The standard Uniform Land Use Review Procedure steps, with the dates the City recorded for this application. Times run from the land use application's filing date. Older applications often have only a few dates on record.
Applicant Team
Environmental review CEQR 82-306R · zoning map amendment C830300ZMR.
Source: the NYC Department of City Planning's Zoning Application Portal, project P1983R0270, as of 2026-11-19. The law firm and consultant are as the City's documents name them. The map outline is the City's map of zoning changes.