Riverdale Greenbelt
85-239X: REZONING R6 TO R2.
- Outcome
- Approved
- Zoning map ULURP
- C850729ZMX
- Rezoned area
- 5.1 acres
- Law firm
- —
Timeline
1 year, 3 months from filing to approval11 months to certification · 4 months of public review
Application and environmental review11 months
- Application filedMar 21, 1985The applicant files the land use application with the Department of City Planning.
- Environmental reviewMar 21, 1985 · through Jul 5, 1985An environmental assessment, or for big projects a full impact statement, under City Environmental Quality Review.
- Certified for public reviewFeb 24, 1986 · CertifiedThe Planning Commission certifies the application complete, and the public review clock starts.
ULURP public review4 months
- Community boardApr 14, 1986 · ApprovedUp to 60 days for the community board's advisory recommendation.
- Borough presidentNo date on recordUp to 30 days for the borough president's recommendation.
- City Planning Commission hearingMay 14, 1986 · Hearing ClosedThe Planning Commission's public hearing.
- City Planning Commission voteJun 4, 1986 · ApprovalThe Planning Commission votes within 60 days of the borough president's review.
- City CouncilThe Council reviews rezonings and votes within 50 days.
- MayorThe mayor may veto within 5 days; the Council can override.
- ApprovedJul 17, 1986
The standard Uniform Land Use Review Procedure steps, with the dates the City recorded for this application. Times run from the land use application's filing date. Older applications often have only a few dates on record.
Applicant Team
ApplicantCbx08Other Public Agency
Environmental review CEQR 85-239X · zoning map amendment C850729ZMX.
Source: the NYC Department of City Planning's Zoning Application Portal, project P1985X0696, as of 2026-11-19. The law firm and consultant are as the City's documents name them. The map outline is the City's map of zoning changes.
See Top NYC Rezoning Attorneys and which NYC condos were built on rezoned land.