Timeline
4 years, 9 months from filing to approval28 days to certification · 4 years, 8 months of public review
Application and environmental review28 days
- Application filedNov 21, 2005The applicant files the land use application with the Department of City Planning.
- Environmental reviewDec 18, 1986 · through Feb 4, 1991An environmental assessment, or for big projects a full impact statement, under City Environmental Quality Review.
- Certified for public reviewDec 19, 2005The Planning Commission certifies the application complete, and the public review clock starts.
ULURP public review4 years, 8 months
- Community boardNo date on recordUp to 60 days for the community board's advisory recommendation.
- Borough presidentNo date on recordUp to 30 days for the borough president's recommendation.
- City Planning Commission hearingNo date on recordThe Planning Commission's public hearing.
- City Planning Commission voteDec 19, 2005 · ApprovalThe Planning Commission votes within 60 days of the borough president's review.
- City CouncilThe Council reviews rezonings and votes within 50 days.
- MayorThe mayor may veto within 5 days; the Council can override.
- ApprovedSep 10, 2010
The standard Uniform Land Use Review Procedure steps, with the dates the City recorded for this application. Times run from the land use application's filing date. Older applications often have only a few dates on record.
Applicant Team
Environmental review CEQR 87-151Q · zoning map amendment M890367AZMQ.
Source: the NYC Department of City Planning's Zoning Application Portal, project P2006Q0182, as of 2026-11-19. The law firm and consultant are as the City's documents name them. The map outline is the City's map of zoning changes.