THE CONDO BOOK PROJECT

Rudin W Village Proj/Form. Svmc

Rezoned areaCondo buildingsBasemap: Esri, HERE, Garmin, © OpenStreetMap contributors

10DCP003M: SVCMC IS SEEKING A NUMBER OF DISCRETIONARY ACTIONS IN CONNEC TION WITH THE CONSTRUCTION OF ITS PROPOSED NEW ACUTE CARE HO SPITAL AND TRAUMA CENTER

Outcome
Approved
Zoning map ULURP
C120033ZMM
Rezoned area
3.1 acres
Law firm
—

Timeline

1 year from filing to approval12 days to certification · 1 year of public review

Application and environmental review12 days

  1. Application filedAug 10, 2011The applicant files the land use application with the Department of City Planning.
  2. Environmental reviewAug 6, 2009 · through Aug 19, 2011An environmental assessment, or for big projects a full impact statement, under City Environmental Quality Review.
  3. Certified for public reviewAug 22, 2011 · CertifiedThe Planning Commission certifies the application complete, and the public review clock starts.

ULURP public review1 year

  1. Community boardOct 26, 2011 · Approved with ConditionsUp to 60 days for the community board's advisory recommendation.
  2. Borough presidentNov 25, 2011 · Conditional FavorableUp to 30 days for the borough president's recommendation.
  3. City Planning Commission hearingNov 30, 2011 · Hearing ClosedThe Planning Commission's public hearing.
  4. City Planning Commission voteJan 23, 2012 · ApprovalThe Planning Commission votes within 60 days of the borough president's review.
  5. City CouncilApr 3, 2012 · AdoptedThe Council reviews rezonings and votes within 50 days.
  6. MayorApr 3, 2012 · No VetoThe mayor may veto within 5 days; the Council can override.
  7. ApprovedAug 27, 2012

The standard Uniform Land Use Review Procedure steps, with the dates the City recorded for this application. Times run from the land use application's filing date. Older applications often have only a few dates on record.

Applicant Team

ApplicantSt. Vincent'S Catholic Medical Center Of NYPrivate applicant

Environmental review CEQR 10DCP003M · zoning map amendment C120033ZMM.

Condo Buildings Here

1 NYC condo building with an offering plan accepted after this rezoning took effect stand on its blocks or inside its area.

CondominiumAcceptedUnitsWhere
Greenwich Lane140-160 West 12th St & 133-155 West 11th St · Manhattan2013200On the rezoned blocks

City Documents

Environmental review81 documents
Hearings and presentations1 document
Other1 document

Source: the NYC Department of City Planning's Zoning Application Portal, project P2012M0017, as of 2026-11-19. The law firm and consultant are as the City's documents name them. The map outline is the City's map of zoning changes.