0.9 acres
Law firm
—

Timeline

1 year, 7 months from filing to approval2 months to certification · 1 year, 4 months of public review

Application and environmental review2 months

  1. Application filedApr 13, 1978The applicant files the land use application with the Department of City Planning.
  2. Certified for public reviewJun 19, 1978 · CertifiedThe Planning Commission certifies the application complete, and the public review clock starts.

ULURP public review1 year, 4 months

  1. Community boardAug 28, 1978 · Non-ComplyingUp to 60 days for the community board's advisory recommendation.
  2. City Planning Commission hearingOct 4, 1978 · Hearing ClosedThe Planning Commission's public hearing.
  3. City Planning Commission voteOct 25, 1978 · ApprovalThe Planning Commission votes within 60 days of the borough president's review.
  4. City CouncilThe Council reviews rezonings and votes within 50 days.
  5. MayorThe mayor may veto within 5 days; the Council can override.
  6. ApprovedNov 18, 1979

The standard Uniform Land Use Review Procedure steps, with the dates the City recorded for this application. Times run from the land use application's filing date. Older applications often have only a few dates on record.

Applicant Team

ApplicantMavronicolas, JamesPrivate applicant

Source: the NYC Department of City Planning's Zoning Application Portal, project P1978Q0469, as of 2026-11-19. The law firm and consultant are as the City's documents name them. The map outline is the City's map of zoning changes.