REZONE FROM R7-1 TO 68-3 IN CONJUNCTION W/WAREHOUSE*EXPANSION & POOR HOUSING SITE

Outcome
Approved
Zoning map ULURP
C840300ZMX
Rezoned area
2.4 acres
Law firm
—

Timeline

4 months from filing to approval11 days to certification · 4 months of public review

Application and environmental review11 days

  1. Application filedOct 20, 1983The applicant files the land use application with the Department of City Planning.
  2. Environmental reviewMar 22, 1983An environmental assessment, or for big projects a full impact statement, under City Environmental Quality Review.
  3. Certified for public reviewOct 31, 1983 · CertifiedThe Planning Commission certifies the application complete, and the public review clock starts.

ULURP public review4 months

  1. Community boardJan 9, 1984 · Non-ComplyingUp to 60 days for the community board's advisory recommendation.
  2. City Planning Commission hearingJan 18, 1984 · Hearing ClosedThe Planning Commission's public hearing.
  3. City Planning Commission voteJan 18, 1984 · ApprovalThe Planning Commission votes within 60 days of the borough president's review.
  4. City CouncilThe Council reviews rezonings and votes within 50 days.
  5. MayorThe mayor may veto within 5 days; the Council can override.
  6. ApprovedMar 15, 1984

The standard Uniform Land Use Review Procedure steps, with the dates the City recorded for this application. Times run from the land use application's filing date. Older applications often have only a few dates on record.

Applicant Team

ApplicantDcpDepartment of City Planning

Environmental review CEQR 83-080X · zoning map amendment C840300ZMX.

Source: the NYC Department of City Planning's Zoning Application Portal, project P1984X0262, as of 2026-11-19. The law firm and consultant are as the City's documents name them. The map outline is the City's map of zoning changes.