Skyway Hotel
86-315Q: ELIMINATION OF 23RD ROAD TO ENABLE PROVISIONS FOR PARKING LOT TO AN EXISTING HOTEL.
- Outcome
- Approved
- Zoning map ULURP
- C880213ZMQ
- Rezoned area
- 2.7 acres
- Law firm
- —
Timeline
4 years, 5 months from filing to approval3 years, 11 months to certification · 6 months of public review
Application and environmental review3 years, 11 months
- Application filedSep 11, 1987The applicant files the land use application with the Department of City Planning.
- Environmental reviewJun 2, 1986An environmental assessment, or for big projects a full impact statement, under City Environmental Quality Review.
- Certified for public reviewAug 12, 1991 · CertifiedThe Planning Commission certifies the application complete, and the public review clock starts.
ULURP public review6 months
- Community boardOct 21, 1991 · Received after Clock ExpiredUp to 60 days for the community board's advisory recommendation.
- Borough presidentNov 20, 1991 · UnfavorableUp to 30 days for the borough president's recommendation.
- City Planning Commission hearingDec 4, 1991 · Hearing ClosedThe Planning Commission's public hearing.
- City Planning Commission voteJan 8, 1992 · ApprovalThe Planning Commission votes within 60 days of the borough president's review.
- City CouncilFeb 11, 1992 · AdoptedThe Council reviews rezonings and votes within 50 days.
- MayorFeb 16, 1992 · No VetoThe mayor may veto within 5 days; the Council can override.
- ApprovedFeb 16, 1992
The standard Uniform Land Use Review Procedure steps, with the dates the City recorded for this application. Times run from the land use application's filing date. Older applications often have only a few dates on record.
Applicant Team
Environmental review CEQR 86-315Q · zoning map amendment C880213ZMQ.
Source: the NYC Department of City Planning's Zoning Application Portal, project P1988Q0180, as of 2026-11-19. The law firm and consultant are as the City's documents name them. The map outline is the City's map of zoning changes.