Sotheby'S Expnsn
86-101M: REZONING HQ SPECIAL PERMIT AND ZONING TEXT CHANGE
- Outcome
- Approved
- Zoning map ULURP
- C861028ZMM
- Rezoned area
- 2.7 acres
- Law firm
- —
Timeline
4 years, 3 months from filing to approval3 years, 9 months to certification · 5 months of public review
Application and environmental review3 years, 9 months
- Application filedMay 7, 1986The applicant files the land use application with the Department of City Planning.
- Environmental reviewNo date on recordAn environmental assessment, or for big projects a full impact statement, under City Environmental Quality Review.
- Certified for public reviewFeb 26, 1990 · CertifiedThe Planning Commission certifies the application complete, and the public review clock starts.
ULURP public review5 months
- Community boardApr 30, 1990 · Non-ComplyingUp to 60 days for the community board's advisory recommendation.
- Borough presidentNo date on recordUp to 30 days for the borough president's recommendation.
- City Planning Commission hearingJun 27, 1990 · Hearing ClosedThe Planning Commission's public hearing.
- City Planning Commission voteJun 27, 1990 · ApprovalThe Planning Commission votes within 60 days of the borough president's review.
- City CouncilThe Council reviews rezonings and votes within 50 days.
- MayorThe mayor may veto within 5 days; the Council can override.
- ApprovedAug 16, 1990
The standard Uniform Land Use Review Procedure steps, with the dates the City recorded for this application. Times run from the land use application's filing date. Older applications often have only a few dates on record.
Applicant Team
Environmental review CEQR 86-101M · zoning map amendment C861028ZMM.
Source: the NYC Department of City Planning's Zoning Application Portal, project P1986M0874, as of 2026-11-19. The law firm and consultant are as the City's documents name them. The map outline is the City's map of zoning changes.