Soundview Partners Apartments
This is a public application by NYCHA requesting a rezoning from R5 to R6 to facilitate residential construction (238 units) with community facility space (1,541 sf) and a Chairperson's certification pursuant to ZR section 62-811 that no waterfront public access area or visual corridors are required, in the Soundview section of CD 9.
- Outcome
- Approved
- Zoning map ULURP
- C120173ZMX
- Rezoned area
- 14.1 acres
- Law firm
- —
Timeline
10 months from filing to approval3 months to certification · 6 months of public review
Application and environmental review3 months
- Application filedJan 19, 2012The applicant files the land use application with the Department of City Planning.
- Environmental reviewNo date on recordAn environmental assessment, or for big projects a full impact statement, under City Environmental Quality Review.
- Certified for public reviewApr 23, 2012 · CertifiedThe Planning Commission certifies the application complete, and the public review clock starts.
ULURP public review6 months
- Community boardJun 22, 2012 · ApprovedUp to 60 days for the community board's advisory recommendation.
- Borough presidentJul 16, 2012 · FavorableUp to 30 days for the borough president's recommendation.
- City Planning Commission hearingJul 25, 2012 · Hearing ClosedThe Planning Commission's public hearing.
- City Planning Commission voteAug 22, 2012 · ApprovalThe Planning Commission votes within 60 days of the borough president's review.
- City CouncilSep 24, 2012 · AdoptedThe Council reviews rezonings and votes within 50 days.
- MayorSep 29, 2012 · No VetoThe mayor may veto within 5 days; the Council can override.
- ApprovedNov 21, 2012
The standard Uniform Land Use Review Procedure steps, with the dates the City recorded for this application. Times run from the land use application's filing date. Older applications often have only a few dates on record.
Applicant Team
Environmental review CEQR 12CHA001X · zoning map amendment C120173ZMX.
Source: the NYC Department of City Planning's Zoning Application Portal, project P2012X0215, as of 2026-11-19. The law firm and consultant are as the City's documents name them. The map outline is the City's map of zoning changes.