Southeast Corner Of E149 St Timpson Pl
CHANGE R7-1 TO C8-3 TO PERMIT TRUCK SALES & REPAIRS
- Outcome
- Approved
- Zoning map ULURP
- C820192ZMX
- Rezoned area
- 2 acres
- Law firm
- —
Timeline
8 months from filing to approval3 months to certification · 4 months of public review
Application and environmental review3 months
- Application filedAug 21, 1981The applicant files the land use application with the Department of City Planning.
- Environmental reviewNo date on recordAn environmental assessment, or for big projects a full impact statement, under City Environmental Quality Review.
- Certified for public reviewDec 7, 1981 · CertifiedThe Planning Commission certifies the application complete, and the public review clock starts.
ULURP public review4 months
- Community boardJan 28, 1982 · ApprovedUp to 60 days for the community board's advisory recommendation.
- Borough presidentNo date on recordUp to 30 days for the borough president's recommendation.
- City Planning Commission hearingFeb 24, 1982 · Hearing ClosedThe Planning Commission's public hearing.
- City Planning Commission voteMar 24, 1982 · ApprovalThe Planning Commission votes within 60 days of the borough president's review.
- City CouncilThe Council reviews rezonings and votes within 50 days.
- MayorThe mayor may veto within 5 days; the Council can override.
- ApprovedApr 29, 1982
The standard Uniform Land Use Review Procedure steps, with the dates the City recorded for this application. Times run from the land use application's filing date. Older applications often have only a few dates on record.
Applicant Team
ApplicantMilea Truck SalesPrivate applicant
Source: the NYC Department of City Planning's Zoning Application Portal, project P1982X0170, as of 2026-11-19. The law firm and consultant are as the City's documents name them. The map outline is the City's map of zoning changes.
See Top NYC Rezoning Attorneys and which NYC condos were built on rezoned land.