87-199Q: REZONE FROM R4 TO R5 FOR EXIST GARDEN DEV TO PERM FOR CONVERSION OF CURRENTLY VACANT BASEMENT SPACE INTO 40 COOP APTS FOR MODERATE INCOME FAMILIES. TB2186.TL2,38,75,88.
- Outcome
- Approved
- Zoning map ULURP
- C870568ZMQ
- Rezoned area
- 13.1 acres
- Law firm
- —
Timeline
2 years from filing to approval1 year, 1 month to certification · 11 months of public review
Application and environmental review1 year, 1 month
- Application filedJan 26, 1987The applicant files the land use application with the Department of City Planning.
- Environmental reviewJan 26, 1987An environmental assessment, or for big projects a full impact statement, under City Environmental Quality Review.
- Certified for public reviewFeb 29, 1988 · CertifiedThe Planning Commission certifies the application complete, and the public review clock starts.
ULURP public review11 months
- Community boardMay 3, 1988 · ApprovedUp to 60 days for the community board's advisory recommendation.
- Borough presidentNo date on recordUp to 30 days for the borough president's recommendation.
- City Planning Commission hearingMay 18, 1988 · Hearing ClosedThe Planning Commission's public hearing.
- City Planning Commission voteJun 15, 1988 · ApprovalThe Planning Commission votes within 60 days of the borough president's review.
- City CouncilThe Council reviews rezonings and votes within 50 days.
- MayorThe mayor may veto within 5 days; the Council can override.
- ApprovedFeb 14, 1989
The standard Uniform Land Use Review Procedure steps, with the dates the City recorded for this application. Times run from the land use application's filing date. Older applications often have only a few dates on record.
Applicant Team
Environmental review CEQR 87-199Q · zoning map amendment C870568ZMQ.
Condo Buildings Here
1 NYC condo building with an offering plan accepted after this rezoning took effect stand on its blocks or inside its area.
| Condominium | Accepted | Units | Where |
|---|---|---|---|
| Lakeview Terrace Condominium65-06 Grand Central Parkway · Queens | 2011 | 13 | On the rezoned blocks |
Source: the NYC Department of City Planning's Zoning Application Portal, project P1987Q0495, as of 2026-11-19. The law firm and consultant are as the City's documents name them. The map outline is the City's map of zoning changes.
See Top NYC Rezoning Attorneys and which NYC condos were built on rezoned land.