Tides At Charleston
REZONE M3-1 & M1-1 TO R3-2 & M1-1 TO ALLOW CONSTRUCTION OF*193 RESD'L UNITS
- Outcome
- Approved
- Zoning map ULURP
- C030449ZMR
- Rezoned area
- 56.3 acres
- Law firm
- —
Timeline
1 year, 5 months from filing to approval11 months to certification · 6 months of public review
Application and environmental review11 months
- Application filedApr 30, 2003The applicant files the land use application with the Department of City Planning.
- Environmental reviewJul 7, 1999An environmental assessment, or for big projects a full impact statement, under City Environmental Quality Review.
- Certified for public reviewApr 12, 2004 · CertifiedThe Planning Commission certifies the application complete, and the public review clock starts.
ULURP public review6 months
- Community boardMay 4, 2004 · ApprovedUp to 60 days for the community board's advisory recommendation.
- Borough presidentMay 6, 2004 · FavorableUp to 30 days for the borough president's recommendation.
- City Planning Commission hearingJun 9, 2004 · Hearing ClosedThe Planning Commission's public hearing.
- City Planning Commission voteJul 14, 2004 · ApprovalThe Planning Commission votes within 60 days of the borough president's review.
- City CouncilAug 12, 2004 · AdoptedThe Council reviews rezonings and votes within 50 days.
- MayorAug 17, 2004 · No VetoThe mayor may veto within 5 days; the Council can override.
- ApprovedOct 19, 2004
The standard Uniform Land Use Review Procedure steps, with the dates the City recorded for this application. Times run from the land use application's filing date. Older applications often have only a few dates on record.
Applicant Team
Environmental review CEQR 95DCP058AR · zoning map amendment C030449ZMR.
Source: the NYC Department of City Planning's Zoning Application Portal, project P2003R0377, as of 2026-11-19. The law firm and consultant are as the City's documents name them. The map outline is the City's map of zoning changes.