Totten'S Landing
85-103R: LARGE SCALE RESIDENTIAL DEVELOPMENT WITH 117 DWELLING UNITS, LANDFILL & VARIOUS MAPPING ACTIONS.
- Outcome
- Approved
- Zoning map ULURP
- I870589ZMR
- Rezoned area
- —
- Law firm
- —
Timeline
11 months from filing to approval11 months to certification · 0 days of public review
Application and environmental review11 months
- Application filedJan 29, 1987The applicant files the land use application with the Department of City Planning.
- Environmental reviewNov 8, 1984 · through Mar 29, 1985An environmental assessment, or for big projects a full impact statement, under City Environmental Quality Review.
- Certified for public reviewJan 22, 1988The Planning Commission certifies the application complete, and the public review clock starts.
ULURP public review0 days
- Community boardUp to 60 days for the community board's advisory recommendation.
- Borough presidentUp to 30 days for the borough president's recommendation.
- City Planning Commission hearingThe Planning Commission's public hearing.
- City Planning Commission voteThe Planning Commission votes within 60 days of the borough president's review.
- City CouncilThe Council reviews rezonings and votes within 50 days.
- MayorThe mayor may veto within 5 days; the Council can override.
- ApprovedJan 22, 1988
The standard Uniform Land Use Review Procedure steps, with the dates the City recorded for this application. Times run from the land use application's filing date. Older applications often have only a few dates on record.
Applicant Team
Environmental review CEQR 85-103R · zoning map amendment I870589ZMR.
Source: the NYC Department of City Planning's Zoning Application Portal, project P1987R0509, as of 2026-11-19. The law firm and consultant are as the City's documents name them. The map outline is the City's map of zoning changes.