Van Wyck Shelter
87-163Q: SHELTER FOR 300 HOMELESS MEN TO PROVIDE ON-SITE SOCIAL SERVICES ON A 24-HR BASIS. TB9970. TL38.
- Outcome
- Approved
- Zoning map ULURP
- C870709ZMQ
- Rezoned area
- —
- Law firm
- —
Timeline
1 year from filing to approval7 months to certification · 4 months of public review
Application and environmental review7 months
- Application filedMar 3, 1987The applicant files the land use application with the Department of City Planning.
- Environmental reviewJan 6, 1987 · through Dec 14, 1987An environmental assessment, or for big projects a full impact statement, under City Environmental Quality Review.
- Certified for public reviewNov 2, 1987 · CertifiedThe Planning Commission certifies the application complete, and the public review clock starts.
ULURP public review4 months
- Community boardJan 11, 1988 · Non-ComplyingUp to 60 days for the community board's advisory recommendation.
- Borough presidentNo date on recordUp to 30 days for the borough president's recommendation.
- City Planning Commission hearingJan 20, 1988 · Hearing ClosedThe Planning Commission's public hearing.
- City Planning Commission voteFeb 17, 1988 · ApprovalThe Planning Commission votes within 60 days of the borough president's review.
- City CouncilThe Council reviews rezonings and votes within 50 days.
- MayorThe mayor may veto within 5 days; the Council can override.
- ApprovedMar 10, 1988
The standard Uniform Land Use Review Procedure steps, with the dates the City recorded for this application. Times run from the land use application's filing date. Older applications often have only a few dates on record.
Applicant Team
Environmental review CEQR 87-163Q · zoning map amendment C870709ZMQ.
Source: the NYC Department of City Planning's Zoning Application Portal, project P1987Q0621, as of 2026-11-19. The law firm and consultant are as the City's documents name them. The map outline is the City's map of zoning changes.