Via Verde/The Green Way

Rezoned areaBasemap: Esri, HERE, Garmin, © OpenStreetMap contributors

UDAAP & DISPO FOR A MIXED USE DEVELOPMENT

Outcome
Approved
Zoning map ULURP
C080517ZMX
Rezoned area
4.3 acres
Law firm
—

Timeline

5 months from filing to approval6 days to certification · 5 months of public review

Application and environmental review6 days

  1. Application filedJun 24, 2008The applicant files the land use application with the Department of City Planning.
  2. Certified for public reviewJun 30, 2008 · CertifiedThe Planning Commission certifies the application complete, and the public review clock starts.

ULURP public review5 months

  1. Community boardJul 31, 2008 · ApprovedUp to 60 days for the community board's advisory recommendation.
  2. Borough presidentAug 21, 2008 · FavorableUp to 30 days for the borough president's recommendation.
  3. City Planning Commission hearingSep 10, 2008 · Hearing ClosedThe Planning Commission's public hearing.
  4. City Planning Commission voteOct 7, 2008 · ApprovalThe Planning Commission votes within 60 days of the borough president's review.
  5. City CouncilDec 18, 2008 · AdoptedThe Council reviews rezonings and votes within 50 days.
  6. MayorDec 23, 2008 · No VetoThe mayor may veto within 5 days; the Council can override.
  7. ApprovedDec 23, 2008

The standard Uniform Land Use Review Procedure steps, with the dates the City recorded for this application. Times run from the land use application's filing date. Older applications often have only a few dates on record.

Applicant Team

ApplicantHpdOther Public Agency

Environmental review CEQR 08HPD018X · zoning map amendment C080517ZMX.

Source: the NYC Department of City Planning's Zoning Application Portal, project P2008X0356, as of 2026-11-19. The law firm and consultant are as the City's documents name them. The map outline is the City's map of zoning changes.

See Top NYC Rezoning Attorneys and which NYC condos were built on rezoned land.