W175th St, University Ave, Tenney Pl, Andrews Ave
94DCP026X: REZONE R7-1 TO C1-4 TO EXTEND THE EXISTING C1-2 COMM'L DIST TO CONSTRUCT A 2-STORY COM'L BLDG; Additional Other #(s): 96DCP0018X
- Outcome
- Approved
- Zoning map ULURP
- I940337ZMX
- Rezoned area
- —
- Law firm
- —
Timeline
1 year, 2 months from filing to approval1 year, 2 months to certification · 0 days of public review
Application and environmental review1 year, 2 months
- Application filedJan 25, 1994The applicant files the land use application with the Department of City Planning.
- Environmental reviewApr 12, 1994An environmental assessment, or for big projects a full impact statement, under City Environmental Quality Review.
- Certified for public reviewMar 29, 1995The Planning Commission certifies the application complete, and the public review clock starts.
ULURP public review0 days
- Community boardUp to 60 days for the community board's advisory recommendation.
- Borough presidentUp to 30 days for the borough president's recommendation.
- City Planning Commission hearingThe Planning Commission's public hearing.
- City Planning Commission voteThe Planning Commission votes within 60 days of the borough president's review.
- City CouncilThe Council reviews rezonings and votes within 50 days.
- MayorThe mayor may veto within 5 days; the Council can override.
- ApprovedMar 29, 1995
The standard Uniform Land Use Review Procedure steps, with the dates the City recorded for this application. Times run from the land use application's filing date. Older applications often have only a few dates on record.
Applicant Team
Environmental review CEQR 94DCP026X · zoning map amendment I940337ZMX.
Source: the NYC Department of City Planning's Zoning Application Portal, project P1994X0267, as of 2026-11-19. The law firm and consultant are as the City's documents name them. The map outline is the City's map of zoning changes.
See Top NYC Rezoning Attorneys and which NYC condos were built on rezoned land.