West 106th Street Rezoning
Rezoning of the block bounded by West 106th and 105th Streets and Amsterdam and Columbus Avenues from R7-2 to R8A and R8B.
- Outcome
- Approved
- Zoning map ULURP
- C130208ZMM
- Rezoned area
- 3.8 acres
- Law firm
- —
Timeline
1 year, 3 months from filing to approval9 months to certification · 6 months of public review
Application and environmental review9 months
- Application filedMar 4, 2013The applicant files the land use application with the Department of City Planning.
- Environmental reviewDec 11, 2013 · through Dec 13, 2013An environmental assessment, or for big projects a full impact statement, under City Environmental Quality Review.
- Certified for public reviewDec 16, 2013 · CertifiedThe Planning Commission certifies the application complete, and the public review clock starts.
ULURP public review6 months
- Community boardFeb 24, 2014 · ApprovedUp to 60 days for the community board's advisory recommendation.
- Borough presidentMar 25, 2014 · FavorableUp to 30 days for the borough president's recommendation.
- City Planning Commission hearingApr 2, 2014 · Hearing ClosedThe Planning Commission's public hearing.
- City Planning Commission voteMay 21, 2014 · ApprovalThe Planning Commission votes within 60 days of the borough president's review.
- City CouncilJul 1, 2014 · AdoptedThe Council reviews rezonings and votes within 50 days.
- MayorJul 1, 2014 · No VetoThe mayor may veto within 5 days; the Council can override.
- ApprovedJul 1, 2014
The standard Uniform Land Use Review Procedure steps, with the dates the City recorded for this application. Times run from the land use application's filing date. Older applications often have only a few dates on record.
Applicant Team
Environmental review CEQR 14DCP084M · zoning map amendment C130208ZMM.
City Documents
Environmental review3 documents
- Certified EAS Dec 11, 2013
- Lead Agency Letter Dec 13, 2013
- Negative Declaration Dec 16, 2013
Source: the NYC Department of City Planning's Zoning Application Portal, project P2012M0285, as of 2026-11-19. The law firm and consultant are as the City's documents name them. The map outline is the City's map of zoning changes.