THE CONDO BOOK PROJECT
Rezoned areaCondo buildingsBasemap: Esri, HERE, Garmin, © OpenStreetMap contributors
Outcome
Approved
Zoning map ULURP
C010123ZMK
Rezoned area
7.3 acres
Law firm
—

Timeline

6 months from filing to approval1 month to certification · 5 months of public review

Application and environmental review1 month

  1. Application filedSep 25, 2000The applicant files the land use application with the Department of City Planning.
  2. Environmental reviewSep 27, 2000 · through Oct 26, 2000An environmental assessment, or for big projects a full impact statement, under City Environmental Quality Review.
  3. Certified for public reviewNov 13, 2000 · CertifiedThe Planning Commission certifies the application complete, and the public review clock starts.

ULURP public review5 months

  1. Community boardJan 10, 2001 · ApprovedUp to 60 days for the community board's advisory recommendation.
  2. Borough presidentFeb 8, 2001 · Conditional FavorableUp to 30 days for the borough president's recommendation.
  3. City Planning Commission hearingFeb 14, 2001 · Hearing ClosedThe Planning Commission's public hearing.
  4. City Planning Commission voteMar 14, 2001 · ApprovalThe Planning Commission votes within 60 days of the borough president's review.
  5. City CouncilApr 17, 2001 · AdoptedThe Council reviews rezonings and votes within 50 days.
  6. MayorApr 23, 2001 · No VetoThe mayor may veto within 5 days; the Council can override.
  7. ApprovedApr 23, 2001

The standard Uniform Land Use Review Procedure steps, with the dates the City recorded for this application. Times run from the land use application's filing date. Older applications often have only a few dates on record.

Applicant Team

ApplicantHpdOther Public Agency

Environmental review CEQR 01HPD001K · zoning map amendment C010123ZMK.

Condo Buildings Here

1 NYC condo building with an offering plan accepted after this rezoning took effect stand inside its area.

CondominiumAcceptedUnitsWhere
Lucky Yeung Condominium161 Jefferson Street · Brooklyn20118In the rezoned area

Source: the NYC Department of City Planning's Zoning Application Portal, project P2001K0099, as of 2026-11-19. The law firm and consultant are as the City's documents name them. The map outline is the City's map of zoning changes.