THE CONDO BOOK PROJECT

Willets Pt Blvd & Cross Island Pkwy

Rezoned areaBasemap: Esri, HERE, Garmin, © OpenStreetMap contributors

CHANGE R3-2 TO R3-1 FOR REZONING OF FORT TOTTEN

Outcome
Approved
Zoning map ULURP
C820965ZMQ
Rezoned area
211.3 acres
Law firm
—

Timeline

5 months from filing to approval7 days to certification · 4 months of public review

Application and environmental review7 days

  1. Application filedApr 26, 1982The applicant files the land use application with the Department of City Planning.
  2. Certified for public reviewMay 3, 1982 · CertifiedThe Planning Commission certifies the application complete, and the public review clock starts.

ULURP public review4 months

  1. Community boardJul 12, 1982 · ApprovedUp to 60 days for the community board's advisory recommendation.
  2. City Planning Commission hearingAug 11, 1982 · Hearing ClosedThe Planning Commission's public hearing.
  3. City Planning Commission voteSep 1, 1982 · ApprovalThe Planning Commission votes within 60 days of the borough president's review.
  4. City CouncilThe Council reviews rezonings and votes within 50 days.
  5. MayorThe mayor may veto within 5 days; the Council can override.
  6. ApprovedSep 30, 1982

The standard Uniform Land Use Review Procedure steps, with the dates the City recorded for this application. Times run from the land use application's filing date. Older applications often have only a few dates on record.

Applicant Team

ApplicantDcpDepartment of City Planning

Source: the NYC Department of City Planning's Zoning Application Portal, project P1982Q0848, as of 2026-11-19. The law firm and consultant are as the City's documents name them. The map outline is the City's map of zoning changes.