Woodhaven Blvd Rezoning
86-282Q: REZONING AREA FROM M1-1 TO M1-2 TO PERMIT EXPANSION OF EXISTING MANUFACTURING FACILITIES.
- Outcome
- Approved
- Zoning map ULURP
- C861003ZMQ
- Rezoned area
- 3 acres
- Law firm
- —
Timeline
1 year, 3 months from filing to approval10 months to certification · 4 months of public review
Application and environmental review10 months
- Application filedMay 2, 1986The applicant files the land use application with the Department of City Planning.
- Environmental reviewMay 14, 1986An environmental assessment, or for big projects a full impact statement, under City Environmental Quality Review.
- Certified for public reviewMar 16, 1987 · CertifiedThe Planning Commission certifies the application complete, and the public review clock starts.
ULURP public review4 months
- Community boardMay 18, 1987 · DisapprovedUp to 60 days for the community board's advisory recommendation.
- Borough presidentNo date on recordUp to 30 days for the borough president's recommendation.
- City Planning Commission hearingJul 13, 1987 · Hearing ClosedThe Planning Commission's public hearing.
- City Planning Commission voteJul 13, 1987 · ApprovalThe Planning Commission votes within 60 days of the borough president's review.
- City CouncilThe Council reviews rezonings and votes within 50 days.
- MayorThe mayor may veto within 5 days; the Council can override.
- ApprovedAug 13, 1987
The standard Uniform Land Use Review Procedure steps, with the dates the City recorded for this application. Times run from the land use application's filing date. Older applications often have only a few dates on record.
Applicant Team
Environmental review CEQR 86-282Q · zoning map amendment C861003ZMQ.
Source: the NYC Department of City Planning's Zoning Application Portal, project P1986Q0850, as of 2026-11-19. The law firm and consultant are as the City's documents name them. The map outline is the City's map of zoning changes.