Woodside Rezoning

REZONE R6A, R6B, R5B TO R4A & R6B TO BETTER REFLECT THE*BUILT CHARACTER OF A 1 & 2 FAMILY ENCLAVE

Outcome
Approved
Zoning map ULURP
I020126ZMQ
Rezoned area
—
Law firm
—

Timeline

5 years, 8 months from filing to approval5 years, 8 months to certification · 0 days of public review

Application and environmental review5 years, 8 months

  1. Application filedSep 28, 2001The applicant files the land use application with the Department of City Planning.
  2. Certified for public reviewMay 31, 2007The Planning Commission certifies the application complete, and the public review clock starts.

ULURP public review0 days

  1. Community boardUp to 60 days for the community board's advisory recommendation.
  2. Borough presidentUp to 30 days for the borough president's recommendation.
  3. City Planning Commission hearingThe Planning Commission's public hearing.
  4. City Planning Commission voteThe Planning Commission votes within 60 days of the borough president's review.
  5. City CouncilThe Council reviews rezonings and votes within 50 days.
  6. MayorThe mayor may veto within 5 days; the Council can override.
  7. ApprovedMay 31, 2007

The standard Uniform Land Use Review Procedure steps, with the dates the City recorded for this application. Times run from the land use application's filing date. Older applications often have only a few dates on record.

Applicant Team

ApplicantQueens Cb2Other Public Agency

Source: the NYC Department of City Planning's Zoning Application Portal, project P2002Q0079, as of 2026-11-19. The law firm and consultant are as the City's documents name them. The map outline is the City's map of zoning changes.