THE CONDO BOOK PROJECT

344 Bowery Condominium

344 Bowery, Manhattan, NY 10012

Compare

Overview

344 Bowery is a 5-unit condo in Manhattan, with 5 storage units and 2 commercial units.

  • Offering plan: Accepted October 2006 · 330 pages
  • Finishes: Wood floors, laminate kitchen countertops, plastic laminate cabinets, Sub-Zero, Viking and Bosch appliances, a washer and dryer in each apartment and central forced air for heating and cooling
  • Prices: $1,198 a square foot on average, as first offered; $13.9 million in all ($13 million when first offered)
  • Common charges: $711–$948 a month, the sponsor's first-year estimate
  • Utilities: Electricity, gas, heat and hot water paid by the owner; water and sewer in the common charges p. 21
  • Developer: Northstar Property Group; principals David L. Berger, Benjamin Braka and Gregory L. Belew
  • Sponsor: 344 Bowery Associates LLC, represented by Lester Bleckner & Shaw LLP
  • Neighborhood: East Village, Manhattan
  • Subway: 4-minute walk to Broadway-Lafayette St/Bleecker St (6, B, D, F, M); 5 minutes to 2 Av (F)
  • Amendments: 5, the latest in December 2007
  1. AcceptedOctober 2006
  2. 5 amendments
  3. First sale
  4. Latest sale

Sales

5 of 5 units sold (100%)

$88.8 millionin sales
$8,888/SFaverage sale price
Jan 8888 – Jan 8888first to latest sale
UnitSoldPrice
PHApr 11, 2008$3,864,259
FLOOR 5Jan 88, 8888$8,888,888
FLOOR 2Jan 8, 8888$8,888,888
FLOOR 3Jan 8, 8888$8,888,888
FLOOR 4Jan 8, 8888$8,888,888
CU1Jan 88, 8888$8,888,888
CU2Jan 8, 8888$888,888
Every sale: 7 recorded sales, with price and dateGet Full Access

From city records (ACRIS), through Jul 31, 2026.

Common Charges & First-Year Budget

Property Taxes

The plan's first-year tax estimate, checked against the city's real bills.

HomePlan's estimateCurrent
FLOOR 2$11,179$26,502FY2026
FLOOR 3$88,888$88,888FY8888
FLOOR 4$88,888$88,888FY8888
FLOOR 5$88,888$88,888FY8888
PH$88,888$88,888FY8888

The plan's estimate is the sponsor's guess for year one. The city's bill is the real one, from the Department of Finance.

Each home's estimate, city bills and tax breaksGet Full Access

Closing Costs

The buyer pays the NYC and NY State transfer taxes, which a seller usually pays.

Sponsor's counsel fee
$1,300Paid by the purchaser to the sponsor's attorneys for the closingp. 78
Counsel's extra charges
  • “$888 per closing”: closing outside Sponsor's attorney's officep. 88
  • $888: cancellation of purchase agreementp. 88
Transfer taxes
Paid by the purchaserNew York City and State transfer taxes, by law the seller's, shift to the buyer in a sponsor salep. 88
Working capital
“four (8) months of Common Charges”Contribution to the condominium's working capital fundp. 88
Deed recording fee
“approximately $888”p. 88
Power of Attorney recording fee
“approximately $888”p. 88

Not listed: title insurance, mortgage tax, lender fees, mansion tax.

All 7 closing costs in the plan, with their pagesGet Full Access

Amendments

Amendment 5 Dec 7, 2007

The OCR text is too garbled to identify any changes this amendment makes to the plan.

Amendment 8 Jan 88, 8888

The amendment text is unreadable OCR noise with no legible words, so no changes to the plan can be identified.

Amendment 8 Jan 8, 8888

This second amendment raises the total offering price and sets new prices for Units 8, 8, 8, 8 and PH.

  • Total offering price increased (the prior and new totals are not legible in this copy)
  • Unit 8 price set at $8,888,888
  • Unit 8 price set at $8,888,888
  • Unit 8 price set at $8,888,888
  • Unit 8 price set at $8,888,888
  • PH price set at $8,888,888
  • Schedule A prices increased for 8 home (median +88.8%): PH $8,888,888 → $8,888,888
What each amendment changed, line by lineGet Full Access

Team

Sponsor
344 Bowery Associates LLC
Developer
Northstar Property Group
Principals
David L. Berger, Benjamin Braka, Gregory L. Belew
Tax estimate
Jerome MazurskyPrepared the first-year real estate tax projection
Construction lender
Bank of Smithtown$6.5 million recorded
Structural engineers
Lane Engineering, Lane Engineering Consulting, P.C.Named on p. 142, p. 182
MEP engineer
Lane Engineering Consulting, P.C.Mechanical, electrical and plumbing · Named on p. 182
Property report
Eric Sheffield ArchitectPrepared the plan's description of the property and its condition · Named on p. 182
Interior designer
Francisca TrujilloReported by 6sqft.com

Zoning

Zoning district
C6-1

Today's zoning, from city data (PLUTO 26v2).

Nearby