Culver El
NYC DCP and HPD propose the culver el project, a series of actions that includes a zoning map amendment, text amendment, special permit, disposition
- Outcome
- Approved
- Zoning map ULURP
- C100345ZMK
- Rezoned area
- 24.1 acres
- Law firm
- —
Timeline
5 months from filing to approval6 days to certification · 5 months of public review
Application and environmental review6 days
- Application filedMay 4, 2010The applicant files the land use application with the Department of City Planning.
- Environmental reviewMay 7, 2010An environmental assessment, or for big projects a full impact statement, under City Environmental Quality Review.
- Certified for public reviewMay 10, 2010 · CertifiedThe Planning Commission certifies the application complete, and the public review clock starts.
ULURP public review5 months
- Community boardJun 24, 2010 · ApprovedUp to 60 days for the community board's advisory recommendation.
- Borough presidentJul 26, 2010 · Conditional FavorableUp to 30 days for the borough president's recommendation.
- City Planning Commission hearingJul 28, 2010 · Hearing ClosedThe Planning Commission's public hearing.
- City Planning Commission voteAug 25, 2010 · ApprovalThe Planning Commission votes within 60 days of the borough president's review.
- City CouncilOct 27, 2010 · AdoptedThe Council reviews rezonings and votes within 50 days.
- MayorNov 3, 2010 · No VetoThe mayor may veto within 5 days; the Council can override.
- ApprovedNov 3, 2010
The standard Uniform Land Use Review Procedure steps, with the dates the City recorded for this application. Times run from the land use application's filing date. Older applications often have only a few dates on record.
Applicant Team
Environmental review CEQR 10DCP029K · zoning map amendment C100345ZMK.
Condo Buildings Here
3 NYC condo buildings with an offering plan accepted after this rezoning took effect stand inside its area.
| Condominium | Accepted | Units | Where |
|---|---|---|---|
| 1269 38th Street Condominium1269 38th Street · Brooklyn | 2022 | 4 | In the rezoned area |
| Culver Developments 1a & 1b Condominium1204-1232 And 1264-1276 37th Street · Brooklyn | 2021 | 36 | In the rezoned area |
| 13/38th Street Condominium1309,1311,1313,1315,1317,1319 & 1321 38th St · Brooklyn | 2015 | 21 | In the rezoned area |
Source: the NYC Department of City Planning's Zoning Application Portal, project P2010K0210, as of 2026-11-19. The law firm and consultant are as the City's documents name them. The map outline is the City's map of zoning changes.
See Top NYC Rezoning Attorneys and which NYC condos were built on rezoned land.