A private rezoning from M1-1 to R6A to facilitate a mixed-use (residential and community facility) development in Brooklyn, Community District 12.

Outcome
Approved
Zoning map ULURP
C090154ZMK
Rezoned area
2.6 acres
Law firm
—

Timeline

4 years, 4 months from filing to approval3 years, 10 months to certification · 6 months of public review

Application and environmental review3 years, 10 months

  1. Application filedOct 20, 2008The applicant files the land use application with the Department of City Planning.
  2. Environmental reviewAug 25, 2010 · through Aug 29, 2012An environmental assessment, or for big projects a full impact statement, under City Environmental Quality Review.
  3. Certified for public reviewSep 4, 2012 · CertifiedThe Planning Commission certifies the application complete, and the public review clock starts.

ULURP public review6 months

  1. Community boardOct 23, 2012 · Approved with ConditionsUp to 60 days for the community board's advisory recommendation.
  2. Borough presidentNov 23, 2012 · Conditional FavorableUp to 30 days for the borough president's recommendation.
  3. City Planning Commission hearingNov 28, 2012 · Hearing ClosedThe Planning Commission's public hearing.
  4. City Planning Commission voteJan 22, 2013 · ApprovalThe Planning Commission votes within 60 days of the borough president's review.
  5. City CouncilFeb 27, 2013 · AdoptedThe Council reviews rezonings and votes within 50 days.
  6. MayorMar 4, 2013 · No VetoThe mayor may veto within 5 days; the Council can override.
  7. ApprovedMar 4, 2013

The standard Uniform Land Use Review Procedure steps, with the dates the City recorded for this application. Times run from the land use application's filing date. Older applications often have only a few dates on record.

Applicant Team

ApplicantFairmont Lanes LLCPrivate applicant

Environmental review CEQR 11DCP022K · zoning map amendment C090154ZMK.

Condo Buildings Here

13 NYC condo buildings with an offering plan accepted after this rezoning took effect stand on its blocks or inside its area.

CondominiumAcceptedUnitsWhere
1555 61st Street Condominium1555 61st Street · Brooklyn202111On the rezoned blocks
1567 61st Street Condominium1567 61st Street · Brooklyn202111On the rezoned blocks
1571 61st Street Condominium1571 61st Street · Brooklyn202111On the rezoned blocks
1559 61st Street Condominium1559 61st Street · Brooklyn202111On the rezoned blocks
1563 61st Street Condominium1563 61st Street · Brooklyn202111On the rezoned blocks
1575 61st Street Condominium1575 61st Street · Brooklyn202011On the rezoned blocks
1570 60th Street Condominium1570 60th Street · Brooklyn20196On the rezoned blocks
1574 60th Street Condominium1574 60th Street · Brooklyn20196On the rezoned blocks
1578 60th Street Condominium1578 60th Street · Brooklyn20196On the rezoned blocks
6004 16th Avenue Condominium6004 16th Avenue · Brooklyn201911On the rezoned blocks
6010 16th Avenue Condominium6010 16th Avenue · Brooklyn201911On the rezoned blocks
6014 16th Avenue Condominium6014 16th Avenue · Brooklyn201911On the rezoned blocks
6020 16th Avenue Condominium6020 16th Avenue · Brooklyn201911On the rezoned blocks

City Documents

Environmental review3 documents

Source: the NYC Department of City Planning's Zoning Application Portal, project P2012K0047, as of 2026-11-19. The law firm and consultant are as the City's documents name them. The map outline is the City's map of zoning changes.